Estimated Completion Time of Novita Residence 7

2021/06/21 11:59:05

2020

18 August

3rd Floor Concrete Pouring

13 August

3rd Floor Concrete Pouring

16 July

2nd Floor Concrete Pouring

16 July

1st Floor Concrete Pouring

13 July

Basement and Ground Floor Concrete Casting

23 June

Elevator Shaft and Foundation Casting.

13 June

Foundation Concrete Casting

19 May

Excavation Work Completed

14 May

Site Layout and Foundation Excavation